Custom Cabinets
Context:
We had to cancel plumbing, relocate thermostat, and finish tile floor prior to installing cabinets. The cabinets in the area below the staircase required speciality drawer glides/hardware to accommodate the extra deep drawers. The cabinet had a custom therma-foil finish.
Scope:
Demo and haul away partially remaining cabinets in living room built-in bar area. Install new custom cabinets.
A. Demolition and Site Preparation
Timeline: 1 day
Carefully remove and haul away all remaining existing cabinetry and debris from the living room bar area.
Protect surrounding finishes (floors, walls, staircase, adjacent furniture) during demolition.
Patch and prepare wall surfaces as needed after cabinet removal.
Cap any abandoned plumbing lines related to the previous bar sink, ensuring code-compliant termination.
B. Pre-Installation Modifications and Preparation
Timeline: 2–3 days
Plumbing Cancellation:
Remove or permanently cap existing water and drain plumbing to eliminate unused sink lines.
Ensure wall and floor areas are properly patched and ready for cabinetry installation.
Thermostat Relocation:
Remove and reinstall the existing thermostat to a new location per Client approval and HVAC manufacturer guidelines.
Run any new low-voltage wiring as necessary, patch old thermostat location.
Tile Flooring Completion:
Prepare subfloor as needed where cabinets were previously removed.
Install matching tile flooring in the open bar area to ensure a continuous floor surface.
Grout and finish tile to match existing finish as closely as practicable.
C. Cabinet Installation
Timeline: 3–4 days
Deliver and inspect custom cabinets for damage and fit prior to installation.
Install new custom cabinetry in bar area, ensuring:
Cabinets are level, plumb, securely fastened to wall studs and/or blocking.
Precise fit under the staircase where cabinet dimensions may be irregular.
Install specialty drawer glides and hardware for extra-deep drawers under the staircase:
Heavy-duty slides rated appropriately for extended drawer length and weight.
Adjust drawer glides to ensure smooth, stable operation.
Handle and install cabinetry with care to maintain custom Therma-foil finish integrity.
Prevent scratches, heat exposure, or surface delamination during install.
D. Finishing Touches and Final Adjustments
Timeline: 1–2 days
Install cabinet hardware (pulls, knobs) per approved layout.
Make final adjustments to doors and drawers for proper alignment and functionality.
Perform thorough cleaning of cabinetry surfaces and surrounding areas.
Conduct a final walk-through with Client to verify fit, finish, and operation.
Overall Project Timeline Estimate:
Approximately 7–10 working days, depending on cabinet delivery timing, site conditions, and specialty hardware installation needs.